    Smyrna Well Project Wells 39 & 40
    Submitting Company
    City of Ceres
    Bid Walk Information
    Bid Opening Date
    08.15.12
    Estimated Cost
    $1,070,000.00
    Estimator
    Steve Murphy
    Description
      The work to be done includes the furnishing of all plant, labor, materials, tools, equipments, testing, and incidentals necessary to complete all the work provided for in the Plans, Specification, and Contract Documents for the SMYRNA WELL PROJECT WELLS 39 & 40, consisting of construction of two (2) new domestic water wells at Smyrna Park including, but not limited  to: Discharge Piping, Drain Piping, Perimeter Fence (with gates), two (2) 1,000 gpm Submersible Pumps and Motors, Chemical Storage and Metering Shelter, Motor Control Center, Standby Generator, Miscellaneous piping, valves, supports, conduit, wiring and associated work.  
    Construction Documents
    Plans
    Specifications
    Additions & Updates