• Past Projects
    Past Project Detail

    Title
    Blaker Well 32 Improvements Project
    Submitting Company
    City of Ceres
    Bid Walk Information

    Non-Mandatory pre-bid Wednesday, November 28, 2012 at 10:00 AM

    Bid Opening Date
    12.11.12
    Estimated Cost
    $1,260,000.00
    Estimator
    Steve Murphy
    Description

    The Work covers constructing a backwash recovery tank, constructing a drain pump station and pipeline to the wastewater treatment plant headworks, replacing the chemical feed system with new chemical facility, modifying the booster pump station HVAC system, replacing the booster pump station flowmeter, demolishing the existing propane tank, replacing the existing generator, modifying the plant site and fences, and performing related required work, located as shown on these Drawings and Specifications.

    Construction Documents
    Plans
    Specifications
    Additions & Updates