• Past Projects
    Past Project Detail

    Title
    Well No. 19R, Well Construction and Pump Station Construction Project
    Submitting Company
    City of Ceres
    Bid Walk Information

    September 21, 2009 at 10:00 a.m.

    Bid Opening Date
    10.06.09
    Estimated Cost
    Estimator
    John Onken
    Description

    The work to be performed under this Contract consists of furnishing all labor, materials and equipment for the construction, development and testing of one (1) municipal water supply well, with a design capacity of 2,000 gpm, including but not limited to site preparation, conductor casing and sanitary seal, borehole drilling, geophysical logging, casing installation, gravel envelope placement, transition and annular seals, well development and testing, disinfection, and/or other work as necessary to complete the project as described in the Plans and Specifications. The borehole depth is approximately 340 feet below ground surface. Install a lockable steel cover on the existing Well 19.

    Construction Documents
    Specifications
    Additions & Updates